Bowdoinham adds lighting change order to waterfront project
Trusted by teams at
Description
The Town of Bowdoinham approved Change Order No. 6 with Bedard Excavation to install additional light poles and fixtures for the Waterfront Improvements Phase 2 project. The amendment adds $34,680.00 to the contract, bringing the total to $840,020.00, with contract completion now set for December 1, 2026.
Contract Details
Contract Amount
Increase of this Change Order: $34,680.00 (new total contract price $840,020.00)
Vendor
BEDARD EXCAVATION
Agency
Town of Bowdoinham, ME
Contract Type
CONSTRUCTION
Document Date
April 9, 2026
Contract Term
Ready for Final Payment extended to December 1, 2026
Renewal Date
2026-12-01
Renewal Info
Change Order No. 6 amends the original 2025 construction contract and prior Change Orders 1–5, increasing the price to $840,020.00 without extending days beyond the revised Ready for Final Payment date of December 1, 2026.
More from BEDARD EXCAVATION
More from Town of Bowdoinham
Town of Bowdoinham Contract Curbside Waste Pick-up and Transportation Contract 2026-07-01
Town of Bowdoinham Select Board Agenda 2026-05-26
Town of Bowdoinham Select Board Agenda 2026-05-26
Town of Bowdoinham Select Board Agenda 2026-05-26
Town of Bowdoinham Select Board Agenda 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.