Birnie Ave Water Main Project Contract Amended
Trusted by teams at
Description
The Commission approved Change Order No. 1 to the contract with Baltazar Contractors Inc. for the Birnie Avenue Water Transmission Main Improvements Project, adding $1,133,578.74 and extending the project by one year to June 23, 2026.
Contract Details
Contract Amount
$1,133,578.74 (Change Order No. 1); New contract total: $5,784,368.74
Vendor
BALTAZAR CONTRACTORS INC
Agency
Springfield Water And Sewer Commission, MA
Contract Type
CONSTRUCTION
Document Date
November 21, 2024
Contract Term
Extended by 365 calendar days; New completion date June 23, 2026
Renewal Date
2026-06-23
Renewal Info
This is Change Order No. 1. Extends contract by 365 days and increases total amount. Original contract was $4,650,790.00; now $5,784,368.74.
More from BALTAZAR CONTRACTORS INC
Issuing Agency
Special District
Springfield, MA
More from Springfield Water And Sewer Commission
Springfield Water and Sewer Commission Meeting Minutes November 2024
Springfield Water and Sewer Commission Meeting Minutes November 2024
Springfield Water and Sewer Commission Meeting Minutes November 2024
Springfield Water and Sewer Commission Meeting Minutes November 2024
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.