SLB Pipe Solutions Contract Extended for Fort Harrison Project
Trusted by teams at
Description
The City of Lawrence approved Change Order No. 01 with SLB Pipe Solutions for the Fort Harrison Collection System Capacity Improvements – Phase III, extending the substantial completion date to February 5, 2026 with no change in contract price ($1,697,675.00). Readiness for final payment is now scheduled for May 22, 2026.
Contract Details
Contract Amount
$1,697,675.00
Vendor
SLB PIPE SOLUTIONS
Agency
City of Lawrence, IN
Contract Type
CONSTRUCTION
Document Date
April 29, 2026
Contract Term
Original contract substantial completion date: December 19, 2025. New substantial completion date: February 5, 2026. Ready for final payment: New date May 22, 2026.
Renewal Date
2026-05-22
Renewal Info
Change order extends contract completion by 48 days for substantial completion and 28 days for final payment. No change to contract value. This is Change Order No. 01; prior change order history is 'N/A'.
More from SLB PIPE SOLUTIONS
More from City of Lawrence
City of Lawrence Utility Service Board Parking License Agreement 2026-06-01
City of Lawrence Staff Report Variance of Development Standards 2026-05-19
City of Lawrence Board of Public Works and Safety Regular Meeting Agenda 2026-05-14
City of Lawrence Board of Public Works and Safety Regular Meeting Agenda 2026-05-14
City of Lawrence Board of Public Works and Safety Regular Meeting Minutes 2026-05-14
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.