Milwaukee Metropolitan Sewerage District Operations Committee Meeting Agenda Packet May 2026

Additional Change Order Authority Granted for JIWRF Chiller Repairs

$269,710 (base contract; additional change orders up to $50,000 authorized)Milwaukee Metropolitan Sewerage DistrictZIEN SERVICE INCMay 3, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Commission delegated $50,000 in change order authority to the Executive Director for Zien Service, Inc.’s screw-compressor water chiller repair contract at Jones Island WRF. This action supports timely completion of the $269,710 project and preserves critical cooling redundancy without work interruptions.

Contract Details

Contract Amount

$269,710 (base contract; additional change orders up to $50,000 authorized)

Vendor

ZIEN SERVICE INC

Agency

Milwaukee Metropolitan Sewerage District, WI

Contract Type

MAINTENANCE

Document Date

May 3, 2026

Renewal Info

Existing repair contract J06106C03 remains in place; Commission authorizes up to $50,000 in cumulative change orders under Executive Director authority.