Bulkeley Central Admin Change Order #46 Approved
Trusted by teams at
Description
The Hartford School Building Committee approved Change Order #46 for Newfield Construction at Bulkeley High School Central Admin in the amount of $22,765. The work includes building system modifications and signage.
Contract Details
Contract Amount
$22,765.00
Vendor
NEWFIELD CONSTRUCTION
Agency
City of Hartford, CT
Contract Type
CONSTRUCTION
Document Date
May 18, 2026
Contract Term
project closeout by August 2026; contract sum revised to $26,719,348.00
Renewal Date
2026-08-31
Renewal Info
Minor schedule extension referenced to August 2026 for closeout and scope completion.