Suisun-Solano Water Authority Executive Committee Meeting Agenda May 2026

Tank 2A Construction Contract Amended for MIC Repairs

Increase $373,670 (includes $339,700 construction change order plus 10% contingency of $33,970)Solano Water AuthorityRESOURCE DEVELOPMENT COMPANYMay 4, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Suisun-Solano Water Authority proposes to amend the Tank 2A rehabilitation construction contract with Resource Development Company by $373,670 to remediate microbial induced corrosion and complete additional repairs. The increase, funded from the Replacement Reserve Fund, is expected to add approximately 40 working days to the project schedule.

Contract Details

Contract Amount

Increase $373,670 (includes $339,700 construction change order plus 10% contingency of $33,970)

Vendor

RESOURCE DEVELOPMENT COMPANY

Agency

Solano Water Authority, CA

Contract Type

CONSTRUCTION

Document Date

May 4, 2026

Renewal Info

Resolution 26-XX will authorize a $339,700 construction change order plus a 10% contingency of $33,790 for MIC remediation; prior action Resolution 26-04 had already added an extra 10% contingency, bringing current construction contingency to $248,000.