Goodfellow Bros. Contract Amended for River Restoration Project
Trusted by teams at
Description
The City Council approved Change Order 1 to Goodfellow Bros., LLC's contract for the White River Restoration Phase 1 project, increasing the contract by $1,085,000 for additional excavation and extending project duration by 20 working days. The new contract total is $3,878,771.00 plus tax, with completion now set for October 15, 2024.
Contract Details
Contract Amount
$1,085,000 (change order); new total $3,878,771.00 plus applicable tax
Vendor
GOODFELLOW BROTHERS LLC
Agency
City of Sumner, WA
Contract Type
CONSTRUCTION
Document Date
September 16, 2024
Contract Term
Extended by 20 working days; new substantial completion 10/15/2024
Renewal Date
2024-10-15
Renewal Info
First change order; adds $1,085,000 and 20 working days. Waives contractor claims related to temporary bridge issues.
More from GOODFELLOW BROTHERS LLC
More from City of Sumner
City of Sumner City Council Meeting Agenda 2026-05-18
City of Sumner City Council Meeting Agenda 2026-05-18
City of Sumner City Council Meeting Agenda 2026-05-18
City of Sumner AgendaPacket 2026-05-18
City of Sumner City Council Meeting Agenda 2026-05-18
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.