Mount Pleasant City Council Agenda January 2026

Capital Underground Utilities Final Water Project Payment Approved

$415,706.96 (final contract amount, original was $451,895, change order -$36,188.04)City of Mount PleasantCAPITAL UNDERGROUND UTILITIES LLCJanuary 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City Council approved the final pay request and reconciliatory change order for Capital Underground Utilities, LLC, regarding the Housing Authority water main replacement project. The contract was reduced to $415,706.96 from the original $451,895. Work substantially completed on August 20, 2025, and all obligations are met.

Contract Details

Contract Amount

$415,706.96 (final contract amount, original was $451,895, change order -$36,188.04)

Vendor

CAPITAL UNDERGROUND UTILITIES LLC

Agency

City of Mount Pleasant, TX

Contract Type

CONSTRUCTION

Document Date

January 20, 2026

Contract Term

April 21, 2025 – September 19, 2025 plus 31 days (total 121 days for substantial completion)

Renewal Date

2025-09-19

Renewal Info

Change order extended completion by 31 calendar days (total 121 days). No further renewal; project is closed with this final payment.