Capital Underground Utilities Final Water Project Payment Approved
Trusted by teams at
Description
The City Council approved the final pay request and reconciliatory change order for Capital Underground Utilities, LLC, regarding the Housing Authority water main replacement project. The contract was reduced to $415,706.96 from the original $451,895. Work substantially completed on August 20, 2025, and all obligations are met.
Contract Details
Contract Amount
$415,706.96 (final contract amount, original was $451,895, change order -$36,188.04)
Vendor
CAPITAL UNDERGROUND UTILITIES LLC
Agency
City of Mount Pleasant, TX
Contract Type
CONSTRUCTION
Document Date
January 20, 2026
Contract Term
April 21, 2025 – September 19, 2025 plus 31 days (total 121 days for substantial completion)
Renewal Date
2025-09-19
Renewal Info
Change order extended completion by 31 calendar days (total 121 days). No further renewal; project is closed with this final payment.
More from CAPITAL UNDERGROUND UTILITIES LLC
More from City of Mount Pleasant
Mount Pleasant City Council Agenda 2026-06-16
Mount Pleasant City Council Agenda Packet 2026-06-16
Mount Pleasant City Council Agenda 2026-05-19
Mount Pleasant City Council Agenda 2026-05-19
Mount Pleasant City Council Agenda 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.