Engineer outlines wastewater rehabilitation project for bidding

Current budget $793,000; total project estimate with alternatives approx. $1,220,000.00City of OwensvilleARCHER-ELGINOctober 20, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City’s engineer, Archer-Elgin, outlined the planned Wastewater Collection System Rehabilitation Project with an estimated cost up to approximately $1.22 million and a base completion target by June 2026. The Board authorized moving forward with the bidding process based on the engineer’s recommendation.

Contract Details

Contract Amount

Current budget $793,000; total project estimate with alternatives approx. $1,220,000.00

Vendor

ARCHER-ELGIN

Agency

City of Owensville, MO

Contract Type

PROFESSIONAL_SERVICES

Document Date

October 20, 2025

Contract Term

Base contract completion by June 2026 (per planned award schedule)