CONSTRUCTIONAMENDED

Council Approves Change Order for 100 North Utility Project

Vernal City Council approved Change Order #1 with Condie Construction for the 100 North water and sewer replacement project, increasing the contract to $5.4 million to cover additional asphalt and unforeseen utility work. The change also adjusts a UDOT-related milestone and grants two extra days for weather delays.

Status
AMENDED
Document date
July 1, 2026
Contract type
CONSTRUCTION
Vendor
Condie Construction
Agency
City of Vernal · UT

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Increase from $4,839,632.30 to $5,397,450.27
Contract type
CONSTRUCTION
Renewal
First change order increasing contract value and adjusting schedule; future change order anticipated for abandoned four-inch water line, per discussion.
Document type
Agenda
Source document
Vernal City Agenda July 1, 2026

Related contracts

Other contracts from Condie Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Vernal?

Condie Construction was awarded this construction contract by City of Vernal, as recorded on July 1, 2026. The contract value is Increase from $4,839,632.30 to $5,397,450.27.

How much is the Condie Construction contract with City of Vernal worth?

The Condie Construction contract with City of Vernal is valued at Increase from $4,839,632.30 to $5,397,450.27, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Vernal City Agenda July 1, 2026 (Agenda), dated July 1, 2026 from City of Vernal. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Condie Construction hold?

Condie Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Condie Construction's profile

What is City of Vernal currently buying?

Explore City of Vernal's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Vernal's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free