San Francisco Public Utilities Commission Resolution Log 2026-05-27

Moccasin Water Filtration Project Budget and Schedule Raised

Increase of $500,000 for a revised cost limit of $6,595,729San Francisco Public Utilities CommissionSIERRA MOUNTAIN CONSTRUCTION INCMay 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The SFPUC increased cost and time contingencies on Contract HH-1013 with Sierra Mountain Construction, Inc., raising the cost limit to $6,595,729 and duration to 920 days for the Moccasin Compound Water System Filtration Addition.

Contract Details

Contract Amount

Increase of $500,000 for a revised cost limit of $6,595,729

Vendor

SIERRA MOUNTAIN CONSTRUCTION INC

Agency

San Francisco Public Utilities Commission, CA

Contract Type

CONSTRUCTION

Document Date

May 27, 2026

Contract Term

Revised duration limit of 920 calendar days (approximately two years and six months)

Renewal Info

Existing cost contingency increased by $500,000 and duration by 274 days.

More from SIERRA MOUNTAIN CONSTRUCTION INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free