Moccasin Water Filtration Project Budget and Schedule Raised
Trusted by teams at
Description
The SFPUC increased cost and time contingencies on Contract HH-1013 with Sierra Mountain Construction, Inc., raising the cost limit to $6,595,729 and duration to 920 days for the Moccasin Compound Water System Filtration Addition.
Contract Details
Contract Amount
Increase of $500,000 for a revised cost limit of $6,595,729
Vendor
SIERRA MOUNTAIN CONSTRUCTION INC
Agency
San Francisco Public Utilities Commission, CA
Contract Type
CONSTRUCTION
Document Date
May 27, 2026
Contract Term
Revised duration limit of 920 calendar days (approximately two years and six months)
Renewal Info
Existing cost contingency increased by $500,000 and duration by 274 days.
More from SIERRA MOUNTAIN CONSTRUCTION INC
Issuing Agency
Special District
San Francisco, CA
More from San Francisco Public Utilities Commission
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
San Francisco Public Utilities Commission Resolution Log 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.