Mishawaka Board of Public Works & Safety Minutes 2026-05-19

Milestone Contract Amended For Street Overlay Project

Increase of $14,727.47; new total $2,558,067.47Housing Authority of the city of MishawakaMILESTONE CONTRACTORSMay 19, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved Final Change Order #1 with Milestone Contractors for the Community Crossings 2024-2 street patch, mill, and overlay project, adding $14,727.47 for a revised total contract of $2,558,067.47. This amendment finalizes quantities and costs for the completed roadway work.

Contract Details

Contract Amount

Increase of $14,727.47; new total $2,558,067.47

Vendor

MILESTONE CONTRACTORS

Agency

Housing Authority of the city of Mishawaka, IN

Contract Type

CONSTRUCTION

Document Date

May 19, 2026

Renewal Info

Final change order closes out the contract with a total value of $2,558,067.47; no further renewals indicated.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free