Taxiway A and Midfield Ramp Contract to Shafer Contracting

The Duluth Airport Authority is set to award a stipulated-price contract to Shafer Contracting Co., Inc. for Taxiway A Reconstruction – Phase 7 and Midfield Ramp Repair – Phase 4, with a base bid of $10.62 million and a potential total of $14.28 million including alternates. Construction is expected to begin in May 2027 and conclude by September 17, 2027, funded primarily by FAA, MnDOT, MnANG, and MnDOT Aeronautics.

Status
RECOMMENDED
Document date
July 19, 2026
Contract type
CONSTRUCTION
Vendor
Shafer Contracting Co Inc
Agency
Duluth Airport Authority · MN

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$10,620,910.37 (Base Bid Schedules A and C); $14,281,681.72 (Base Bid plus Alternate Schedules A, B, and C contingent on funding)
Contract type
CONSTRUCTION
Contract term
Estimated administrative start August 1, 2026; construction start May 17, 2027; 85 calendar days for Schedule A, additional 30 days for Schedule B if awarded, and 80 calendar days for Schedule C, with substantial completion by September 17, 2027
Renewal date
2027-10-02
Document type
AgendaPacket
Source document
Duluth Airport Authority AgendaPacket Board Meeting 2026-07-21

Related contracts

Other contracts from Shafer Contracting Co Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Duluth Airport Authority?

Shafer Contracting Co Inc was awarded this construction contract by Duluth Airport Authority, as recorded on July 19, 2026. The contract value is $10,620,910.37 (Base Bid Schedules A and C); $14,281,681.72 (Base Bid plus Alternate Schedules A, B, and C contingent on funding).

How much is the Shafer Contracting Co Inc contract with Duluth Airport Authority worth?

The Shafer Contracting Co Inc contract with Duluth Airport Authority is valued at $10,620,910.37 (Base Bid Schedules A and C); $14,281,681.72 (Base Bid plus Alternate Schedules A, B, and C contingent on funding), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Duluth Airport Authority AgendaPacket Board Meeting 2026-07-21 (AgendaPacket), dated July 19, 2026 from Duluth Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Shafer Contracting Co Inc hold?

Shafer Contracting Co Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Shafer Contracting Co Inc's profile

What is Duluth Airport Authority currently buying?

Explore Duluth Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Duluth Airport Authority's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free