Electrical improvements contract with Millo Electrical gains extension, more funds
Trusted by teams at
Description
Change Order No. 1 was ratified for Millo Electrical Contractor Inc. to cover additional costs and a 120-day extension on the Southwest Wellfield Electrical Improvements project, increasing the contract total by $247,628.40.
Contract Details
Contract Amount
$247,628.40 (incremental increase; original contract $5,069,440.00)
Vendor
MILLO ELECTRICAL CONTRACTOR INC
Agency
Miami Hsg Conservation, FL
Contract Type
CONSTRUCTION
Document Date
March 16, 2026
Contract Term
Extended by 120 calendar days; new completion date May 12, 2026
Renewal Date
2026-05-12
Renewal Info
First amendment increases amount and duration from original 560 days to 680 days total.
More from MILLO ELECTRICAL CONTRACTOR INC
More from Miami Hsg Conservation
Board of County Commissioners Agenda March 17 2026
Board of County Commissioners Agenda March 17 2026
Board of County Commissioners Agenda March 17 2026
Board of County Commissioners Agenda March 17 2026
Board of County Commissioners Agenda March 17 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.