Mazanec Construction contract extended with no-cost change

BRAZOS RIVER AUTHORITYMAZANEC CONSTRUCTIONSeptember 29, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Brazos River Authority’s Board previously authorized a construction contract with Mazanec Construction for the Environmental Services Building, with work starting April 1, 2024 and an original completion of December 2025. Due to utility-related delays, Change Order 4 granted a no-cost 120-day extension, moving final completion to May 2026.

Contract Details

Vendor

MAZANEC CONSTRUCTION

Agency

BRAZOS RIVER AUTHORITY, TX

Contract Type

CONSTRUCTION

Document Date

September 29, 2025

Contract Term

Construction term – 660 days beginning April 1, 2024; extended 120 days to new final completion May 2026

Renewal Date

2026-05-31

Renewal Info

Change Order 4 approved a no-cost time extension of 120 days, revising the construction schedule from an original final completion in December 2025 to a new completion date in May 2026.