Mazanec Construction contract extended with no-cost change
Trusted by teams at
Description
The Brazos River Authority’s Board previously authorized a construction contract with Mazanec Construction for the Environmental Services Building, with work starting April 1, 2024 and an original completion of December 2025. Due to utility-related delays, Change Order 4 granted a no-cost 120-day extension, moving final completion to May 2026.
Contract Details
Vendor
MAZANEC CONSTRUCTION
Agency
BRAZOS RIVER AUTHORITY, TX
Contract Type
CONSTRUCTION
Document Date
September 29, 2025
Contract Term
Construction term – 660 days beginning April 1, 2024; extended 120 days to new final completion May 2026
Renewal Date
2026-05-31
Renewal Info
Change Order 4 approved a no-cost time extension of 120 days, revising the construction schedule from an original final completion in December 2025 to a new completion date in May 2026.
More from MAZANEC CONSTRUCTION
More from BRAZOS RIVER AUTHORITY
Brazos River Authority Property Management Committee Agenda March 16 2026
brazos_river_authority_board_of_directors_meeting.pdf
agreement_with_hillco_partners.pdf
possum_kingdom_bay_9_transition_beam_and_weir_box.pdf
brazos_river_authority_board_agenda_september_2025.pdf
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.