City of Portland Board of Mayor and Aldermen Minutes October 2025

Splashpad construction contract extended for completion dates

$0 (time extension only)Portland Housing AuthorityOLYMPIAN CONSTRUCTION COMPANY LLCOctober 20, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board of Mayor and Aldermen approved Resolution 25-72, authorizing Change Order #2 with Olympian Construction Co, LLC for the Richland Park Splashpad project. The change order extends substantial completion to March 12, 2026 and final completion to March 26, 2026 due to soil and supply issues, with no additional cost reported.

Contract Details

Contract Amount

$0 (time extension only)

Vendor

OLYMPIAN CONSTRUCTION COMPANY LLC

Agency

Portland Housing Authority, TN

Contract Type

CONSTRUCTION

Document Date

October 20, 2025

Contract Term

Extension of 124 days to March 12, 2026 for substantial completion and 108 days to March 26, 2026 for final completion

Renewal Date

2026-03-26

Renewal Info

Change Order #2 modifies only the project schedule, extending substantial and final completion dates; officials indicated no further extensions are anticipated.