Change order expands BR Welding plant project
Trusted by teams at
Description
The Township of Ocean Sewerage Authority approved Change Order No. 1 to BR Welding, Inc. for $287,164.90 to replace both Final Clarifier 1 and 2 drive mechanisms at the treatment plant. This amendment raises the total 2025 Treatment Plant Improvements contract value to $2,008,179.90 without extending the September 27, 2026 completion date.
Contract Details
Contract Amount
$287,164.90 (change order); new total $2,008,179.90
Vendor
BR WELDING INC
Agency
Ocean Township SA, NJ
Contract Type
CONSTRUCTION
Document Date
March 3, 2026
Contract Term
Original completion date September 27, 2026; no additional time with Change Order No. 1
Renewal Date
2026-09-27
Renewal Info
Change Order No. 1 increases the contract price from $1,721,015.00 to $2,008,179.90; contract completion date remains September 27, 2026 with no added time.
More from BR WELDING INC
More from Ocean Township SA
Township of Ocean Sewerage Authority Regular Meeting Minutes March 2026
Township of Ocean Sewerage Authority Regular Meeting February 2026
Township of Ocean Sewerage Authority Regular Meeting February 2026
Township of Ocean Sewerage Authority Regular Meeting February 2026
Township of Ocean Sewerage Authority Regular Meeting February 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.