Maury Service Authority Board Meeting Minutes January 2026

Route 11 Waterline Change Order Adds Insert Valve

$26,146.40 (Change Order #2)Maury Service AuthorityRANDY HOSTETTER EXCAVATINGJanuary 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Maury Service Authority approved Change Order #2 with Randy Hostetter Excavating for the Route 11 Water Line Improvements, increasing the contract by $26,146.40 for installation of an insert valve near the Houston Street Tank. The revised contract total is $2,324,918.40 with no additional time.

Contract Details

Contract Amount

$26,146.40 (Change Order #2)

Vendor

RANDY HOSTETTER EXCAVATING

Agency

Maury Service Authority, VA

Contract Type

CONSTRUCTION

Document Date

January 27, 2026

Contract Term

To project completion; substantial completion now March 5, 2026, final payment April 4, 2026

Renewal Date

2026-04-04

Renewal Info

Contract previously at $2,298,772.00. This is the second change; prior modifications included Change Order #1 for time only (+35 days). No change to contract duration with this order. Next renewal/amendment due at project close or new change order.