City of Ephrata City Council Agenda March 18, 2026

Wastewater Plant Upgrade with Clearwater Construction Nears Completion

$9,857,835.08City of EphrataCLEARWATER CONSTRUCTIONMarch 18, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Clearwater Construction continues upgrades to Ephrata’s Wastewater Reclamation Facility under a $9.85 million contract. Final work includes system programming and punch-list completion with overall project nearing substantial completion.

Contract Details

Contract Amount

$9,857,835.08

Vendor

CLEARWATER CONSTRUCTION

Agency

City of Ephrata, WA

Contract Type

CONSTRUCTION

Document Date

March 18, 2026

Contract Term

May 2024 – February 2026

Renewal Date

2026-02-28

Renewal Info

Project began May 2024; substantial completion is in process as of February 2026. No amendments or extensions documented.