Hi-Desert Water District Regular Board Meeting Agenda Packet 2026-06-17

Change Order 003 Extends Sewer Main on Sage Avenue

$253,734.25Hi-Desert Water DistrictSUKUT CONSTRUCTION LLCJune 17, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board is asked to approve Change Order No. 003 with Sukut Construction, LLC for $253,734.25 to extend an 8‑inch sewer main and add three new manholes along Sage Avenue on the Phase II Wastewater Collection System Project. The change accounts for unforeseen field conditions at the connection to the existing sewer and has a 10‑day schedule impact within the current completion date.

Contract Details

Contract Amount

$253,734.25

Vendor

SUKUT CONSTRUCTION LLC

Agency

Hi-Desert Water District, CA

Contract Type

CONSTRUCTION

Document Date

June 17, 2026

Contract Term

Schedule impact 10 days; overall contract completion remains December 30, 2026

Renewal Date

2026-12-30

Renewal Info

Third change order; adds $253,734.25 (0.35%) to construction contract for additional 8‑inch sewer and manholes; noted 10‑day schedule impact without altering the December 30, 2026 completion date.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free