Kenaidan Continues Water Treatment Plant Expansion for New Tecumseth
Trusted by teams at
Description
Kenaidan Contracting Ltd. is delivering the $216.8 million construction contract for the Raymond A. Barker Water Treatment Plant Expansion, with substantial completion milestones extending into 2032 due to schedule impacts and approved change orders.
Contract Details
Contract Amount
$216,800,000 (construction budget)
Vendor
KENAIDAN CONTRACTING LTD
Agency
Town of New Tecumseth, Canada
Contract Type
CONSTRUCTION
Document Date
March 9, 2026
Contract Term
June 3, 2024 – January 15, 2032
Renewal Date
2032-01-15
Renewal Info
Original budget $212.6M, revised $216.8M. Seventeen change orders to date, ongoing progress and quarterly reporting. Project end date revised to January 15, 2032 from original milestone dates.
More from KENAIDAN CONTRACTING LTD
More from Town of New Tecumseth
New Tecumseth Special Council Meeting Agenda 2026-06-17
New Tecumseth Special Council Meeting Agenda 2026-06-17
New Tecumseth Special Council Meeting Agenda 2026-06-17
New Tecumseth Council Agenda 2026-06-15
New Tecumseth Council Agenda 2026-06-15
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.