Third Payment Recommended For GST Replacement Contract
Trusted by teams at
Description
Castlewood Municipal Utility District received Application for Payment No. 3 from Nunn Constructors, Ltd. for $119,250.00 for March 2026 work on the Water Plant No. 1 Ground Storage Tank Replacement. The engineer recommends payment and notes a previously approved 64-day extension that will move substantial completion to September 5, 2026 once formalized.
Contract Details
Contract Amount
$119,250.00
Vendor
NUNN CONSTRUCTORS LTD
Agency
Castlewood Mud, TX
Contract Type
CONSTRUCTION
Document Date
April 14, 2026
Contract Term
Contract date July 29, 2025; substantial completion currently July 3, 2026 with 64-day extension approved by board but not yet added by change order, which would move substantial completion to September 5, 2026.
Renewal Date
2026-09-05
Renewal Info
Construction contract dated July 29, 2025; board has approved a 64-day extension related to surface water piping revisions, pending formalization by change order, which will extend substantial completion to September 5, 2026.
More from NUNN CONSTRUCTORS LTD
More from Castlewood Mud
Castlewood M.U.D. Operations Report 2026-05-21
Castlewood Municipal Utility District Monthly Status Report 2026-05-19
Castlewood Municipal Utility District Monthly Status Report 2026-05-19
Castlewood Municipal Utility District Monthly Status Report 2026-05-19
Castlewood Municipal Utility District Monthly Status Report 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.