The Minneola Community Redevelopment Agency is considering approval of a design-build construction contract with Florida Dock and Boat Lifts, Inc. to design, permit, and construct a new public dock system on Lake Minneola for a guaranteed maximum price of $160,000.00. The contractor will deliver a turnkey, code-compliant pier facility under an 8–10 week construction schedule following permitting and mobilization.
Contract Details
Contract Amount
$160,000.00 (guaranteed maximum price; not to exceed $160,000.00)
Vendor
FLORIDA DOCK AND BOAT LIFTS INC
Agency
City of Minneola, FL
Contract Type
CONSTRUCTION
Document Date
May 5, 2026
Contract Term
Design to final completion; key milestones: permit drawings within 14 days of Notice to Proceed, structural drawings 7 days thereafter, permitting estimated 1–2 months, mobilization within 2–3 weeks of permit issuance, construction completed within 8–10 weeks from commencement; insurance maintained for 12 months after completion; agreement subject to annual appropriation and terminable for convenience
Renewal Info
No explicit renewal or extension options are provided; contract time may be extended only by written change order for force majeure, owner-caused delays, or certain permitting delays. The owner may terminate for convenience or for cause, and funding is subject to annual appropriation.
More from City of Minneola
Minneola City Council Meeting Agenda May 2026
Minneola City Council Meeting Agenda May 2026
Minneola City Council Meeting Agenda May 2026
Minneola City Council Meeting Agenda May 2026
Minneola City Council Meeting Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.