Piping Change Order Approved for Middle School HVAC Project

The Caldwell-West Caldwell Board of Education approved Change Order 001 with William J. Guarini, Inc. for $260,662.00 to replace and reroute HW/CW piping to fixtures at Grover Cleveland Middle School under the existing HVAC and piping replacement project. The change order uses project allowance funds and does not alter the overall contract sum or completion date.

Status
AMENDED
Document date
June 19, 2026
Contract type
CONSTRUCTION
Vendor
William J. Guarini Inc
Agency
Caldwell-West School District · NJ

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$260,662.00 (change order amount); contract sum remains $4,137,000.00
Contract type
CONSTRUCTION
Contract term
Contract time unchanged; substantial completion date unchanged
Renewal
Change Order 001 modifies the scope of the existing general construction contract by adding piping bypass and replacement work funded from the project general allowance, without extending contract time or increasing the overall contract sum.
Document type
Contract
Source document
Caldwell-West Caldwell Board of Education Change Order 10104PIPE - HVAC & HW/HC Piping Replacement at Grover Cleveland Middle School 2026-06-19

Related contracts

Other contracts from William J. Guarini Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Caldwell-West School District?

William J. Guarini Inc was awarded this construction contract by Caldwell-West School District, as recorded on June 19, 2026. The contract value is $260,662.00 (change order amount); contract sum remains $4,137,000.00.

How much is the William J. Guarini Inc contract with Caldwell-West School District worth?

The William J. Guarini Inc contract with Caldwell-West School District is valued at $260,662.00 (change order amount); contract sum remains $4,137,000.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Caldwell-West Caldwell Board of Education Change Order 10104PIPE - HVAC & HW/HC Piping Replacement at Grover Cleveland Middle School 2026-06-19 (Contract), dated June 19, 2026 from Caldwell-West School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does William J. Guarini Inc hold?

William J. Guarini Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View William J. Guarini Inc's profile

What is Caldwell-West School District currently buying?

Explore Caldwell-West School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Caldwell-West School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free