North Marin Water District Agenda Packet 2026-05-05

Joint Novato Blvd Water and Roadway Improvements Move Forward

$5,725,000 (District total project estimate; $4,350,000 construction phase including $2,300,000 contractor water work, $1,300,000 District materials, $300,000 soft costs, $450,000 other construction)North Marin Water DistrictCITY OF NOVATOMay 5, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

North Marin Water District is proceeding under a cost share agreement with the City of Novato for joint roadway and water improvements on Novato Boulevard between Diablo Avenue and Grant Avenue. For the District’s portion, total project costs are estimated at $5.725 million over several fiscal years, with the City managing bidding and construction of the combined contract.

Contract Details

Contract Amount

$5,725,000 (District total project estimate; $4,350,000 construction phase including $2,300,000 contractor water work, $1,300,000 District materials, $300,000 soft costs, $450,000 other construction)

Vendor

CITY OF NOVATO

Agency

North Marin Water District, CA

Contract Type

CONSTRUCTION

Document Date

May 5, 2026

Contract Term

Construction cost share agreement effective 10/10/2025 through 12/31/2028; Joint Project planned to be advertised prior to July 1, 2026, with expenditures over FY 26/27–28/29

Renewal Date

2028-12-31

Renewal Info

Agreement term runs approximately October 10, 2025 through December 31, 2028, covering design integration, bidding, construction, and closeout; future change orders and cost adjustments for water improvements will follow the agreement’s cost-sharing and change-management provisions.