City of Bartlesville City Council Meeting Agenda Packet May 4 2026

Airport Hangar Contract Extended 30 Days With No Cost

City of BartlesvilleKEOHN CONSTRUCTION SERVICESMay 4, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Council will consider Change Order No. 3 with Keohn Construction Services for the Bartlesville Airport box hangar project, adding 30 calendar days to the contract with no budget impact. The extension reflects time needed for additional waterline relocation work completed under a prior change order.

Contract Details

Vendor

KEOHN CONSTRUCTION SERVICES

Agency

City of Bartlesville, OK

Contract Type

CONSTRUCTION

Document Date

May 4, 2026

Contract Term

30 additional calendar days

Renewal Info

Third change order to original August 4, 2025 construction contract; this amendment adjusts only contract time by 30 days without affecting the total contract price.