Amherst County Service Authority Board Meeting Agenda May 5, 2026

James Riverbank stabilization contract increased for culvert work

$1,499,550 (original); Change Order #1 increase $30,000; new total $1,529,550Amherst County Service AuthoritySTONEWALL BRIDGE INCMay 5, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Amherst County Service Authority is asked to approve Change Order #1 with Stonewall Bridge, Inc, increasing the James River Streambank Stabilization Phase 2 construction contract by $30,000 to a revised total of $1,529,550 for installation of two additional culverts and access road improvements. The change addresses stormwater-related erosion risks to sewer infrastructure using remaining grant funds.

Contract Details

Contract Amount

$1,499,550 (original); Change Order #1 increase $30,000; new total $1,529,550

Vendor

STONEWALL BRIDGE INC

Agency

Amherst County Service Authority, VA

Contract Type

CONSTRUCTION

Document Date

May 5, 2026

Renewal Info

Single change order (Change Order #1) increases the original Phase 2 construction contract from $1,499,550 to $1,529,550; no additional term or renewal provisions discussed.