Poulsbo City Council Agenda Summary Complete Streets Curb Ramp Upgrades Project Acceptance 2026-05-06

City Accepts Complete Streets Curb Ramp Upgrade Project

$465,010 initial bid; $19,870 change order; final construction cost $473,180City of PoulsboASPHALT PATCH SYSTEMS INCMay 6, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Poulsbo City Council is asked to formally accept the Complete Streets Curb Ramp Upgrades project constructed by Asphalt Patch Systems, Inc, with a final construction cost of $473,180 after one $19,870 change order. The construction upgraded and installed curb ramps and associated safety improvements at 32 locations and was completed ahead of schedule and under the overall project budget.

Contract Details

Contract Amount

$465,010 initial bid; $19,870 change order; final construction cost $473,180

Vendor

ASPHALT PATCH SYSTEMS INC

Agency

City of Poulsbo, WA

Contract Type

CONSTRUCTION

Document Date

May 6, 2026

Contract Term

Completed June 2025

Renewal Date

2025-06-30

Renewal Info

Single construction contract with one change order of $19,870; no renewals or extensions indicated as project is complete.