147th Signal Project Final Acceptance and Retainage Release
Trusted by teams at
Description
The 147th Signal Project contract with Colacurcio Brothers, Inc., originally awarded for $1,171,830 with $134,548.56 in change orders, reached physical completion on March 18, 2026 with a final construction cost of $1,306,378.56. On June 23, 2026 Council is set to accept the project, start the 45-day lien period, and authorize release of retainage.
Contract Details
Contract Amount
$1,171,830 original construction contract; final construction payment $1,306,378.56
Vendor
COLACURCIO BROTHERS INC
Agency
City of Monroe, WA
Contract Type
CONSTRUCTION
Document Date
June 23, 2026
Contract Term
Construction began September 2, 2025; physical completion March 18, 2026
Renewal Date
2026-08-07
Renewal Info
This is a completed construction contract; acceptance starts a 45-day lien period, after which retainage is released upon receipt of state releases.
More from COLACURCIO BROTHERS INC
More from City of Monroe
Monroe City Council Agenda Packet 2026-06-23
Monroe City Council Agenda Packet 2026-06-23
Monroe City Council Agenda Packet 2026-06-23
Monroe City Council Agenda Packet 2026-06-23
Monroe City Council Agenda Packet 2026-06-23
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.