Grinnell amends WRH water plant construction contract
Trusted by teams at
Description
The Grinnell City Council approved Change Order No. 8 with WRH, Inc. for the Water Treatment Plant Project, adding $146,712.07 for well subcontractor replacement. The amendment extends substantial completion to May 4, 2027 and increases the total construction contract to $19,422,888.27.
Contract Details
Contract Amount
$146,712.07 (net increase; new total $19,422,888.27)
Vendor
WRH INC
Agency
Grinnell Low Rent Housing Authority, IA
Contract Type
CONSTRUCTION
Document Date
May 26, 2026
Contract Term
Contract date December 2, 2024; substantial completion extended from 2/23/2027 to 5/4/2027
Renewal Date
2027-05-04
Renewal Info
Change Order No. 8 increases the construction contract amount by $146,712.07 and extends substantial completion by 70 calendar days to May 4, 2027; prior original contract date was December 2, 2024 with earlier substantial completion of February 23, 2027.
More from WRH INC
Issuing Agency
Local Housing Authority
Grinnell, IA
More from Grinnell Low Rent Housing Authority
iowa-hhs-gemt-provider-participation-agreement_1e2.pdf
iowa-hhs-gemt-uncompensated-cost-prospective-payment-program-agreement_988.pdf
Grinnell Library Board AgendaPacket 2026-05-27
Grinnell Library Board AgendaPacket 2026-05-27
Grinnell Library Board AgendaPacket 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.