Skagit Transit Board of Directors Regular Meeting Agenda Sept 2025

MOA2 contract increase via HB Hansen change orders

$100,901.93Skagit Public Transportation Benefit Area AuthorityHB HANSEN CONSTRUCTIONSeptember 17, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Skagit Transit is considering approval of HB Hansen Construction Change Orders 14 and 15, which together increase the MOA2 Phase 1 contract by $100,901.93 while extending final completion time at no additional cost. The changes address drainage, waterproofing, and a new TPO membrane roof system.

Contract Details

Contract Amount

$100,901.93

Vendor

HB HANSEN CONSTRUCTION

Agency

Skagit Public Transportation Benefit Area Authority, WA

Contract Type

CONSTRUCTION

Document Date

September 17, 2025

Renewal Info

Contract Sum for Contract #19-014-F will be increased by $100,901.93 through Change Orders 14 and 15; contract time for final completion extended at no cost, weather-dependent.

More from HB HANSEN CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free