Time Extension Approved for Nord Pioneer Turnout Project
Trusted by teams at
Description
The Kern County Water Agency approved Change Order No. 3 with MAC General Engineering for the North Pioneer East Basin Turnout Structures Project, extending the contract time by 35 days at no additional cost, keeping the total contract amount at $509,583.00. The extension accommodates delayed slide gate manufacturing and moves the completion date to May 29, 2026.
Contract Details
Contract Amount
$509,583.00
Vendor
MAC GENERAL ENGINEERING
Agency
Kern Co Water Agency, CA
Contract Type
CONSTRUCTION
Document Date
April 23, 2026
Contract Term
Contract Time extended by 35 calendar days to May 29, 2026 (total 292 days)
Renewal Date
2026-05-29
Renewal Info
Change Order No. 3 extends the contract completion date by 35 calendar days with no cost increase, resulting in a revised total contract time of 292 days and a completion date of May 29, 2026.
More from MAC GENERAL ENGINEERING
More from Kern Co Water Agency
Kern County Water Agency Agenda Special Board of Directors Meeting 2026-05-28
Kern County Water Agency Agenda Special Board of Directors Meeting 2026-05-28
Kern County Water Agency Agenda Special Board of Directors Meeting 2026-05-28
Kern County Water Agency Board of Directors Meeting Agenda Packet April 2026
Kern County Water Agency Board of Directors Meeting Agenda Packet April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.