Farley Inc slated for Calderwood culvert project
Trusted by teams at
Description
The Town of Washington expects Farley, Inc. to begin the Calderwood Road culvert construction project on or about July 15, 2026, with a road closure of roughly four and a half weeks. The total project budget is $480,000, funded by the Town, State, and Maine Rivers.
Contract Details
Contract Amount
$480,000.00 total project (Town $25,000.00; State $200,000.00; Maine Rivers estimated $255,000.00)
Vendor
FARLEY INC
Agency
Town of Washington, ME
Contract Type
CONSTRUCTION
Document Date
May 6, 2026
Contract Term
Construction scheduled to start on or about July 15, 2026; road closed for about 4½ weeks
Renewal Date
2026-08-19
More from FARLEY INC
More from Town of Washington
Putnam Select Board Meeting Summary 2026-05-20
Town of Washington Select Board /Assessors Meeting Summary 2026-05-06
Town of Washington Select Board /Assessors Meeting Summary 2026-05-06
Town of Washington Select Board /Assessors Meeting Summary 2026-04-29
Town of Washington Select Board /Assessors Meeting Summary 2026-04-29
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.