White Salmon City Council Meeting Agenda April 2026

Ongoing North Main–Spring Street Contract with Ajax Northwest

$2,257,115.14City of White SalmonAJAX NORTHWEST LLCApril 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Ajax Northwest, LLC continues work under a $2,257,115.14 contract with the City of White Salmon for the North Main–Spring Street Water Improvements. The project includes water line replacements, booster pump station construction, and associated site restoration with a revised completion date of May 1, 2026.

Contract Details

Contract Amount

$2,257,115.14

Vendor

AJAX NORTHWEST LLC

Agency

City of White Salmon, WA

Contract Type

CONSTRUCTION

Document Date

April 13, 2026

Contract Term

Original completion date April 27, 2026; revised to May 1, 2026

Renewal Date

2026-05-01

Renewal Info

Contract has been amended via multiple change orders increasing the original amount of $2,134,634.44 by $122,480.70 and extending completion to May 1, 2026.