CONSTRUCTIONAMENDED

Hazardous Soil Disposal Change Orders Issued for Dos Rios Station

SacRT reported amendments to change orders under its Dos Rios Light Rail Station construction contract with DMZ Builders, including increasing Change Order No. 1 to $157,250 and issuing Change Order No. 7 to remove additional hazardous Type Z-1 soil. The emergency change orders were authorized by the General Manager to prevent costly work interruptions and are funded with state and federal dollars.

Status
AMENDED
Document date
April 28, 2025
Contract type
CONSTRUCTION
Vendor
Dmz Builders
Agency
Sacramento Regional Transit District · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Change Order 1.1: $92,130.00 (total for CCO No. 1 increased to $157,250.00); additional CCO No. 7 amount not specified
Contract type
CONSTRUCTION
Renewal
Change orders issued under General Manager emergency authority to avoid interruption; cumulative change order limits governed by Procurement Ordinance Section 1.506.
Document type
Agenda
Source document
Sacramento Regional Transit District Board Meeting Agenda April 2025

Related contracts

Other contracts from Dmz Builders.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Sacramento Regional Transit District?

Dmz Builders was awarded this construction contract by Sacramento Regional Transit District, as recorded on April 28, 2025. The contract value is Change Order 1.1: $92,130.00 (total for CCO No. 1 increased to $157,250.00); additional CCO No. 7 amount not specified.

How much is the Dmz Builders contract with Sacramento Regional Transit District worth?

The Dmz Builders contract with Sacramento Regional Transit District is valued at Change Order 1.1: $92,130.00 (total for CCO No. 1 increased to $157,250.00); additional CCO No. 7 amount not specified, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Sacramento Regional Transit District Board Meeting Agenda April 2025 (Agenda), dated April 28, 2025 from Sacramento Regional Transit District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Dmz Builders hold?

Dmz Builders may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Dmz Builders's profile

What is Sacramento Regional Transit District currently buying?

Explore Sacramento Regional Transit District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Sacramento Regional Transit District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free