Fiber Construction Project Continues with Midwest Energy & Communication
Trusted by teams at
Description
Berrien County continues its contract with Midwest Energy & Communication for countywide fiber broadband construction, under ARPA and ROBIN funding. The total county contribution is not to exceed $4.5 million, with ARPA funds allocated at $675 per parcel, completion scheduled for Q2 2026.
Contract Details
Contract Amount
Not to exceed $4.5 million (county ARPA allocation: $675 per parcel)
Vendor
MIDWEST ENERGY & COMMUNICATION
Agency
Berrien County, GA
Contract Type
CONSTRUCTION
Document Date
February 5, 2026
Contract Term
Through end of Q2 2026; completion anticipated by June 30, 2026
Renewal Date
2026-06-30
Renewal Info
Funded through ARPA/ROBIN; duration through project completion estimated Q2 2026. Additional parcels such as Camp Madrin Lake Road considered as construction crews are mobilized.
More from MIDWEST ENERGY & COMMUNICATION
More from Berrien County
Berrien County Board of Commissioners Agenda 2026-05-28
Berrien County Board of Commissioners Agenda 2026-05-28
Berrien County Board of Commissioners Resolution Regarding Substance Use Disorder and Prevention Program Funding 2026-05-28
Berrien County Board of Commissioners Resolution Requisition Approval 2026-05-28
Berrien County Board of Commissioners Resolution Requisition Approval 2026-05-28
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.