Berrien County Broadband Internet Task Force Meeting Minutes February 2026

Fiber Construction Project Continues with Midwest Energy & Communication

Not to exceed $4.5 million (county ARPA allocation: $675 per parcel)Berrien CountyMIDWEST ENERGY & COMMUNICATIONFebruary 5, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Berrien County continues its contract with Midwest Energy & Communication for countywide fiber broadband construction, under ARPA and ROBIN funding. The total county contribution is not to exceed $4.5 million, with ARPA funds allocated at $675 per parcel, completion scheduled for Q2 2026.

Contract Details

Contract Amount

Not to exceed $4.5 million (county ARPA allocation: $675 per parcel)

Vendor

MIDWEST ENERGY & COMMUNICATION

Agency

Berrien County, GA

Contract Type

CONSTRUCTION

Document Date

February 5, 2026

Contract Term

Through end of Q2 2026; completion anticipated by June 30, 2026

Renewal Date

2026-06-30

Renewal Info

Funded through ARPA/ROBIN; duration through project completion estimated Q2 2026. Additional parcels such as Camp Madrin Lake Road considered as construction crews are mobilized.