Fort Bend County MUD No. 175 approved two change orders totaling $12,267.35 to increase its construction contract with Wild Magnolia for the Pecan Ridge Phase 3 Streetscape project. The amendments cover additional landscaping and streetscape work as outlined by the landscape architect.
Contract Details
Contract Amount
Change Order No. 11: $6,048.75; Change Order No. 12: $6,218.60 (both increases)
Vendor
WILD MAGNOLIA
Agency
Fort Bend County Mud 175, TX
Contract Type
CONSTRUCTION
Document Date
March 5, 2026
Renewal Info
Two additive change orders (Nos. 11 and 12) increased the contract price for the ongoing Pecan Ridge Phase 3 Streetscape project; no change to term was noted.
More from WILD MAGNOLIA
More from Fort Bend County Mud 175
Fort Bend County Municipal Utility District No. 175 Minutes 2026-04-02
Fort Bend County Municipal Utility District No. 175 Minutes 2026-04-02
Fort Bend County Municipal Utility District No. 175 Minutes March 2026
Fort Bend County Municipal Utility District No. 175 Minutes March 2026
Fort Bend County Municipal Utility District No. 175 Meeting Minutes February 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.