CONSTRUCTIONAMENDED

Fontaine Contract Amended for Turf Field and Terrazzo

The Agawam School Building Committee approved Fontaine’s Contract Amendment #13 and Change Order #01 totaling $2,526,068.45 to add turf field and terrazzo flooring work to the high school project. The additional costs will be funded from the construction contingency and reported to the MSBA.

Status
AMENDED
Document date
June 22, 2026
Contract type
CONSTRUCTION
Vendor
FONTAINE
Agency
City of Agawam · MA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$2,526,068.45
Contract type
CONSTRUCTION
Renewal
Contract Amendment #13 increases Fontaine’s construction contract value by $2,526,068.45 via Change Order #01 funded from construction contingency.
Document type
Minutes
Source document
Agawam School Building Committee Minutes June 22, 2026

Related contracts

Other contracts from FONTAINE.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Agawam?

FONTAINE was awarded this construction contract by City of Agawam, as recorded on June 22, 2026. The contract value is $2,526,068.45.

How much is the FONTAINE contract with City of Agawam worth?

The FONTAINE contract with City of Agawam is valued at $2,526,068.45, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Agawam School Building Committee Minutes June 22, 2026 (Minutes), dated June 22, 2026 from City of Agawam. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does FONTAINE hold?

FONTAINE may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View FONTAINE's profile

What is City of Agawam currently buying?

Explore City of Agawam's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Agawam's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free