S&L Awarded Wastewater Phases 3 & 4 Construction Contract
Trusted by teams at
Description
The City of Thompson Falls awarded S&L the contract for Wastewater System Improvements Phases 3 & 4, covering all remaining unconnected city areas. Construction began September 2025 with project duration of approximately 480 days.
Contract Details
Contract Amount
Not stated; below projected budget (Wastewater Phases 3 & 4)
Vendor
S&L
Agency
City of Thompson Falls, MT
Contract Type
CONSTRUCTION
Document Date
January 12, 2026
Contract Term
Approx. 480 calendar days from 9/22/2025 (Notice to Proceed), covering two construction seasons, with winter shutdowns as needed
Renewal Date
2026-12-16
Renewal Info
Original duration approx. 480 calendar days with allowed seasonal shutdown; no extension or amendment info in the document.
More from S&L
More from City of Thompson Falls
City of Thompson Falls Agenda 2026-06-08
City of Thompson Falls Agenda 2026-06-08
City of Thompson Falls Agenda 2026-06-08
City of Thompson Falls Agenda 2026-06-08
City of Thompson Falls Agenda 2026-06-08
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.