Stayton approves valve chamber change order with Canyon
Trusted by teams at
Description
The Stayton City Council approved Resolution 26-007 authorizing a change order with Canyon Contracting, Inc. to construct a reinforced concrete valve chamber for the 30-inch Water Treatment Facility intake isolation valve. The amendment adds $81,000 in concrete vault work for a total not-to-exceed project cost of $198,000 under a contract running through April 30, 2026. The project enhances the City’s ability to remotely and rapidly isolate its raw water intake in response to Detroit Dam drawdown risks.
Contract Details
Contract Amount
Not-to-exceed $198,000 (includes $117,000 original construction portion plus $81,000 change order)
Vendor
CANYON CONTRACTING INC
Agency
City of Stayton, OR
Contract Type
CONSTRUCTION
Document Date
March 16, 2026
Contract Term
Through final completion date of April 30, 2026
Renewal Date
2026-04-30
Renewal Info
Change Order #1 adds vault design and construction for $81,000 to the original $117,000 construction contract, establishing a revised total contract amount of $198,000 with final completion by April 30, 2026. No further renewal or extension options are described.
More from CANYON CONTRACTING INC
More from City of Stayton
City of Stayton Planning Commission Agenda 2026-05-26
City of Stayton Planning Commission Agenda 2026-05-26
City of Stayton Planning Commission Agenda 2026-05-26
City of Stayton Agenda Stayton Public Library Board Meeting 2026-05-20
City of Stayton City Council Agenda 2026-05-18
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.