CONSTRUCTIONONGOING

Greater Texoma Utility Authority Board Meeting Agenda Packet April 2026

Major Progress Payment to Alterman for Post Oak WWTP Electrical Upgrades

$2,788,045.20Greater Texoma Utility AuthorityALTERMAN INCApril 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Authority will pay Alterman Inc. $2,788,045.20 for Pay Application #2 on the Sherman 2023 Post Oak WWTP Standby Generator and Paralleling Switchgear project, which is 57% complete. This funds continued electrical and standby power improvements at the plant.

Contract Details

Contract Amount

$2,788,045.20

Vendor

ALTERMAN INC

Agency

Greater Texoma Utility Authority, TX

Contract Type

CONSTRUCTION

Document Date

April 20, 2026

Renewal Info

Ongoing construction contract, with progress payments tied to completion milestones; currently 57% complete.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free