City of Bunnell City Commission Meeting Agenda Packet February 2026

Amended Major Construction Contract for Bunnell WWTF BNR Project

Original GMP2 $42,440,006; Revised to $39,142,150.50 (post-CO190006/190001)City of BunnellPC CONSTRUCTION COMPANYFebruary 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

PC Construction Company's contract for Bunnell's $42.4M WWTF BNR Improvements Project was reduced by over $3 million via owner direct purchase deductive change orders, with a new contract amount of $39.1 million.

Contract Details

Contract Amount

Original GMP2 $42,440,006; Revised to $39,142,150.50 (post-CO190006/190001)

Vendor

PC CONSTRUCTION COMPANY

Agency

City of Bunnell, FL

Contract Type

CONSTRUCTION

Document Date

February 23, 2026

Contract Term

Project: WWTF BNR Improvements, ongoing through April 2027

Renewal Date

2027-04-30

Renewal Info

Multiple contract amendments; owner direct purchasing reduces contractor's scope and total due. Target completion April 2027.