C.W. Young Utilities Contract Progress Payment Approved
Trusted by teams at
Description
The District is advancing the Trinity Falls Planning Unit 6, Phase 4 Utilities project under a $2,974,078.00 contract with C.W. Young Construction, Ltd. The Board approved Pay Application No. 3 for $750,751.20 as the project approaches its October 22, 2025 target completion.
Contract Details
Contract Amount
$2,974,078.00
Vendor
C.W. YOUNG CONSTRUCTION LTD
Agency
Collin County Mud 2, TX
Contract Type
CONSTRUCTION
Document Date
October 21, 2025
Contract Term
125 calendar days of construction time; Notice to Proceed June 27, 2025 with anticipated completion October 22, 2025
Renewal Date
2025-10-22
More from C.W. YOUNG CONSTRUCTION LTD
More from Collin County Mud 2
McKinney Municipal Utility District No. 2 of Collin County Minutes April 21, 2026
McKinney Municipal Utility District No. 2 of Collin County Minutes April 21, 2026
McKinney Municipal Utility District No. 2 of Collin County Minutes April 21, 2026
McKinney Municipal Utility District No. 2 of Collin County Minutes April 21, 2026
McKinney Municipal Utility District No. 2 of Collin County Minutes April 21, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.