El Paso Water Public Service Board Meeting Agenda April 2026

Change Order 4 Recommended for CSA Constructors Stormwater Project

$233,788.20El Paso WaterKARLSRUHER INC DBA CSA CONSTRUCTORSApril 8, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

El Paso Water staff recommends approval of Change Order Number 4 with Karlsruher, Inc. dba CSA Constructors for $233,788.20 to enhance stormwater basin infrastructure at the John T. Hickerson Water Reclamation Facility. The change order adds a 60-inch RCP, pond modifications, a protective wall, and extends contract time by 45 days, increasing the cumulative contract amount by 13.58%.

Contract Details

Contract Amount

$233,788.20

Vendor

KARLSRUHER INC DBA CSA CONSTRUCTORS

Agency

El Paso Water, TX

Contract Type

CONSTRUCTION

Document Date

April 8, 2026

Contract Term

Additional 45 days to contract time

Renewal Info

Fourth change order to Bid Number SW71-24; increases cumulative contract amount by 13.58% and extends contract time by 45 days. Prior Change Orders 2 and 3 were approved administratively under the President/CEO’s delegated authority.