city-of-new-haven-application-and-certification-for-payment_e63.pdf

Edgerton Road Watermain contract payment to Bunn Excavating

$4,180,186.37 (original $4,098,006.06 plus net change orders $82,180.31); current payment due $128,974.16City of New HavenBUNN EXCAVATING INCSeptember 11, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of New Haven continues its construction contract with Bunn Excavating, Inc. for the Edgerton Road Watermain Improvements project, with a current contract value of $4,180,186.37 after change orders. Pay Application No. 11 certifies a current payment of $128,974.16 for work performed through August 31, 2025.

Contract Details

Contract Amount

$4,180,186.37 (original $4,098,006.06 plus net change orders $82,180.31); current payment due $128,974.16

Vendor

BUNN EXCAVATING INC

Agency

City of New Haven, IN

Contract Type

CONSTRUCTION

Document Date

September 11, 2025

Contract Term

Contract date 2/6/2024; application period 8/1/2025–8/31/2025

Renewal Info

Construction contract dated 2/6/2024 with ongoing progress payments; change orders have adjusted the original sum by $82,180.31 to date. No explicit renewal or extension terms are stated in the payment application.