Edgerton Road Watermain contract payment to Bunn Excavating
Trusted by teams at
Description
The City of New Haven continues its construction contract with Bunn Excavating, Inc. for the Edgerton Road Watermain Improvements project, with a current contract value of $4,180,186.37 after change orders. Pay Application No. 11 certifies a current payment of $128,974.16 for work performed through August 31, 2025.
Contract Details
Contract Amount
$4,180,186.37 (original $4,098,006.06 plus net change orders $82,180.31); current payment due $128,974.16
Vendor
BUNN EXCAVATING INC
Agency
City of New Haven, IN
Contract Type
CONSTRUCTION
Document Date
September 11, 2025
Contract Term
Contract date 2/6/2024; application period 8/1/2025–8/31/2025
Renewal Info
Construction contract dated 2/6/2024 with ongoing progress payments; change orders have adjusted the original sum by $82,180.31 to date. No explicit renewal or extension terms are stated in the payment application.
More from BUNN EXCAVATING INC
More from City of New Haven
City of New Haven Board of Public Works & Safety Agenda May 2026
City of New Haven Board of Public Works & Safety Agenda May 2026
City of New Haven Board of Public Works & Safety Agenda May 2026
City of New Haven Board of Public Works & Safety Agenda May 5, 2026
City of New Haven Board of Public Works & Safety Agenda May 5, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.