Laney Theater modernization construction change order ratified
Trusted by teams at
Description
Peralta CCD ratified Change Order No. 3 with DL Falk Construction Inc. for $26,433.83 to cover additional demolition, temporary power, and finish removal work on the Laney College Theater Modernization Project. The change order is funded from the existing owner contingency and brings the total contract amount to $29,622,322.38, with the project scheduled through February 2, 2027.
Contract Details
Contract Amount
$26,433.83
Vendor
DL FALK CONSTRUCTION INC
Agency
College Of Alameda, CA
Contract Type
CONSTRUCTION
Document Date
June 23, 2026
Contract Term
Through 2/2/2027
Renewal Date
2027-02-02
Renewal Info
Third change order to this construction contract increases the total contract amount but does not alter the February 2, 2027 completion date. Future change orders will continue to draw from the approved owner contingency.
More from DL FALK CONSTRUCTION INC
More from College Of Alameda
Peralta Community College District Agenda 2026-06-23
Peralta Community College District Agenda 2026-06-23
Peralta Community College District Agenda 2026-06-23
Peralta Community College District Agenda 2026-06-23
Peralta Community College District Agenda 2026-06-23
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.