Peralta Community College District Agenda 2026-06-23

Laney Theater modernization construction change order ratified

$26,433.83College Of AlamedaDL FALK CONSTRUCTION INCJune 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Peralta CCD ratified Change Order No. 3 with DL Falk Construction Inc. for $26,433.83 to cover additional demolition, temporary power, and finish removal work on the Laney College Theater Modernization Project. The change order is funded from the existing owner contingency and brings the total contract amount to $29,622,322.38, with the project scheduled through February 2, 2027.

Contract Details

Contract Amount

$26,433.83

Vendor

DL FALK CONSTRUCTION INC

Agency

College Of Alameda, CA

Contract Type

CONSTRUCTION

Document Date

June 23, 2026

Contract Term

Through 2/2/2027

Renewal Date

2027-02-02

Renewal Info

Third change order to this construction contract increases the total contract amount but does not alter the February 2, 2027 completion date. Future change orders will continue to draw from the approved owner contingency.

More from DL FALK CONSTRUCTION INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free