CONSTRUCTIONAMENDED

City of Austin AgendaPacket City Council Meeting 2026-06-15

WWTP Change Order 012 Approved with Rice Lake Construction Group

($323,434) (credit on Change Order 012); total revised contract $102,958,769.72City of AustinRICE LAKE CONSTRUCTION GROUPJune 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Austin City Council approved Change Order 012 with Rice Lake Construction Group, issuing a $323,434 credit for the Wastewater Treatment Plant expansion. The revised contract stands at $102,958,769.72, with no extension to the contract duration.

Contract Details

Contract Amount

($323,434) (credit on Change Order 012); total revised contract $102,958,769.72

Vendor

RICE LAKE CONSTRUCTION GROUP

Agency

City of Austin, MN

Contract Type

CONSTRUCTION

Document Date

June 15, 2026

Contract Term

August 1, 2022 – Expected substantial completion after 1,524 days

Renewal Info

Multiple change orders to date. No adjustment to completion dates with this amendment. Term started August 1, 2022, with substantial completion in 1,524 days.