Town of Darien Representative Town Meeting Rules Committee Agenda Packet 2026-06-01

Retaining Wall Contract for NHFD Increases by $618,800

$2,624,900 (cumulative, after $618,800 increase and bond authorization)Town of DarienNOROTON HEIGHTS FIRE DEPARTMENTJune 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Town of Darien proposes increasing the total contract and bond for the Noroton Heights Fire Department Retaining Wall Replacement to $2,624,900, reflecting $618,800 in additional costs due to unforeseen conditions and change orders. The amended resolution awaits RTM approval.

Contract Details

Contract Amount

$2,624,900 (cumulative, after $618,800 increase and bond authorization)

Vendor

NOROTON HEIGHTS FIRE DEPARTMENT

Agency

Town of Darien, CT

Contract Type

CONSTRUCTION

Document Date

June 1, 2026

Renewal Info

Original appropriation approved March 17, 2025 ($2,006,100), amended for 501(c)(3) status April 21, 2025, further amended June 2026 for additional $618,800 with new total $2,624,900. Change Order #2 included. Project schedule not specified.