Moorhead City Council Agenda Packet 2026-06-08

Center Avenue Street Reconstruction Contract Awarded

$2,493,261.85 plus up to $105,000 in early completion incentives and up to $124,663.05 in change orders (total authorized contract may reach $2,722,924.90)Town of MoorheadDAKOTA UNDERGROUND COMPANYJune 8, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Moorhead City Council awarded a construction contract valued at $2,493,261.85 to Dakota Underground Company for the Center Avenue Reconstruction from 8th to 10th St, including street, sidewalk, and lighting upgrades. The agreement authorizes incentive and change order payments, with work scheduled for Summer/Fall 2026.

Contract Details

Contract Amount

$2,493,261.85 plus up to $105,000 in early completion incentives and up to $124,663.05 in change orders (total authorized contract may reach $2,722,924.90)

Vendor

DAKOTA UNDERGROUND COMPANY

Agency

Town of Moorhead, MN

Contract Type

CONSTRUCTION

Document Date

June 8, 2026

Contract Term

Anticipated construction schedule: Summer/Fall 2026

Renewal Date

2026-11-30

Renewal Info

Minor change orders up to 5% ($124,663.05) of contract. Early completion incentive up to $105,000 possible.