Metro Water Engineering Committee Report April 2026

Schedule extended for COP Cottonwoods Connection contract

Salt Lake-Sandy Metropolitan Water DistrictCOP CONSTRUCTIONApril 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Metro Water reported Change Order No. AB09 with COP Construction for the Cottonwoods Connection CC-1 and CC-2 work, extending the construction schedule to May 29, 2026 without changing the contract price. The extension accommodates delays in obtaining vault ladders while maintaining the current construction budget.

Contract Details

Vendor

COP CONSTRUCTION

Agency

Salt Lake-Sandy Metropolitan Water District, UT

Contract Type

CONSTRUCTION

Document Date

April 13, 2026

Contract Term

Original construction contract awarded February 26, 2024; extended from February 27, 2026 to May 29, 2026 by Change Order No. AB09

Renewal Date

2026-05-29

Renewal Info

Change Order No. AB09 is a no‑cost time extension, moving substantial completion from February 27, 2026 to May 29, 2026; earlier change orders adjusted scope and reduced overall construction cost.