Schedule extended for COP Cottonwoods Connection contract
Trusted by teams at
Description
Metro Water reported Change Order No. AB09 with COP Construction for the Cottonwoods Connection CC-1 and CC-2 work, extending the construction schedule to May 29, 2026 without changing the contract price. The extension accommodates delays in obtaining vault ladders while maintaining the current construction budget.
Contract Details
Vendor
COP CONSTRUCTION
Agency
Salt Lake-Sandy Metropolitan Water District, UT
Contract Type
CONSTRUCTION
Document Date
April 13, 2026
Contract Term
Original construction contract awarded February 26, 2024; extended from February 27, 2026 to May 29, 2026 by Change Order No. AB09
Renewal Date
2026-05-29
Renewal Info
Change Order No. AB09 is a no‑cost time extension, moving substantial completion from February 27, 2026 to May 29, 2026; earlier change orders adjusted scope and reduced overall construction cost.
More from COP CONSTRUCTION
Issuing Agency
Special District
Cottonwood Heights, UT
More from Salt Lake-Sandy Metropolitan Water District
Metropolitan Water District of Salt Lake & Sandy Agenda Board of Trustees Meeting 2026-06-15
Metropolitan Water District of Salt Lake & Sandy Agenda Board of Trustees Meeting 2026-06-15
Metropolitan Water District of Salt Lake & Sandy Agenda Board of Trustees Meeting 2026-06-15
Metropolitan Water District of Salt Lake & Sandy Engineering Committee Report 2026-06-08
Metropolitan Water District of Salt Lake & Sandy Engineering Committee Report 2026-06-08
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.